[Checklists] CQI for Welding and Painting under IATF 16949
- Kriss Nakhon
- Jul 17, 2025
- 2 min read
internal audit matrix for Welding and Painting processes under IATF 16949, including checklists, required evidence, and automotive-specific examples:
1. Welding Process Audit Matrix
(Aligned with IATF 16949 + AWS D1.1/CQI-15 standards)
Audit Focus | Checklist Question | Evidence to Review | Automotive Example | Compliance |
4.1 Process Validation | Is weld procedure qualification (WPQR) up-to-date? | WPQR records, welder certifications (AWS/ISO 9606). | Resistance spot weld validation for truck chassis. | ✔/✖ |
7.1.5.1 MSA | Are weld nugget measurement tools calibrated (GR&R ≤10%)? | MSA reports, caliper calibration logs. | Ultrasonic weld tester GR&R study. | ✔/✖ |
8.5.1 SPC | Are weld strength tests monitored via control charts? | X-bar R charts, destructive test reports. | Peel test results for door hinges (CpK ≥1.33). | ✔/✖ |
8.5.2 Traceability | Can all welded joints be traced to operator/shift? | Weld logs with barcode/VIN, MES data. | Recall investigation of faulty roof welds. | ✔/✖ |
8.7.1 Non-Conformity | Are cracked welds contained within 1 hour? | Containment reports, quarantine tags. | Laser weld cracks in battery trays. | ✔/✖ |
9.1.2 PFMEA | Is weld spatter (Severity=7) addressed in PFMEA? | PFMEA updates, poka-yoke solutions (anti-spatter gel). | Robot weld gun maintenance logs. | ✔/✖ |
2. Painting Process Audit Matrix
(Aligned with IATF 16949 + CQI-12/VDA 6.3)
Audit Focus | Checklist Question | Evidence to Review | Automotive Example | Compliance |
4.2 Pretreatment | Is chemical bath concentration checked hourly? | Titration logs, pH/conductivity records. | Zinc phosphate coating weight checks. | ✔/✖ |
7.1.5.1 MSA | Is paint thickness gauge GR&R ≤10%? | MSA reports, Elcometer calibration certs. | E-coat thickness measurements. | ✔/✖ |
8.5.1 SPC | Are oven temperature profiles monitored (CpK ≥1.67)? | Control charts, IR sensor data. | Curing oven profile for hood panels. | ✔/✖ |
8.6.1 Final Audit | Is color match verified per customer standards? | Spectrophotometer reports, customer approval samples. | BMW’s "Alpine White" color batch approval. | ✔/✖ |
8.7.1 Defects | Are fisheyes (paint bubbles) documented with RCA? | 8D reports, contamination control checklists. | Dust contamination in clearcoat. | ✔/✖ |
10.2.1 CAPA | Are corrective actions implemented for adhesion failures? | Cross-cut test results, paint supplier corrective actions. | Peeling paint on fenders. | ✔/✖ |
Key Evidence Examples for Welding & Painting
Welding
WPQR (Weld Procedure Qualification Record): Approved parameters for materials/thicknesses.
Destructive Test Samples: Photographs of peel/shear tests.
Weld Seam Tracking: Laser-scanned weld profiles vs. CAD specs.
Painting
Salt Spray Test Reports: 500+ hours corrosion resistance proof.
Color Match Data: ΔE ≤1.0 (spectrophotometer readings).
Paint Viscosity Logs: Adjusted per ambient humidity (ISO cup tests).
Automotive-Specific Requirements
Welding:
IATF 16949 Clause 8.5.1.1: Validate robotic weld programs annually.
Customer CSR: GM’s "Weld Quality Standard GMW14058" for nugget size.
Painting:
IATF 16949 Clause 8.6.2: First/last piece audits for color/gloss.
Customer CSR: Ford’s "Paint Appearance Manual" for orange peel tolerance.
Non-Conformance Examples
Process | NC Finding | IATF Clause | Corrective Action |
Welding | No torque checks on weld gun electrodes. | 7.1.5.1 (MSA) | Implement daily torque audits + digital wrench. |
Painting | E-coat tank contamination (Zn²⁺超标). | 8.5.2 (Traceability) | Filter replacement + batch quarantine. |
Audit Tools & Templates
Welding:
CQI-15 Checklist: [Download Link]
Weld Defect Atlas: For visual standards (porosity, cracks).
Painting:
CQI-12 Checklist: [Download Link]
VDA 6.3 Process Audit Sheet: Focus on P6 (Process Control).
Pro Tips
Use IoT: Monitor weld current/paint booth humidity in real-time.
Layered Audits: Daily checks by supervisors + monthly deep dives.