[Case studies] for Car hood manufacturing defects
- Kriss Nakhon
- Jul 17, 2025
- 2 min read
Analyzed by the 4M framework (Man, Machine, Material, Method) and resolved using quality tools
Car Hood Manufacturing Defects: 4M Analysis & Solutions
(Each case maps a defect type to a root cause (4M) and corrective action with results)
Case | Defect Observed | 4M Root Cause | Quality Tool Used | Corrective Action | Result |
1 | Dents in hood panels | Man: Improper handling by operators. | 5 Whys | - Added foam padding on workstations. - Training on "2-hand carry" technique. | Dents reduced by 85%. |
2 | Weld splatter marks | Machine: Weld gun misalignment. | SPC (Control Charts) | - Calibrated weld guns every shift. - Added real-time monitoring. | Splatter defects down 70%. |
3 | Paint adhesion failure | Material: Contaminated primer. | 8D Problem-Solving | - Supplier audit + batch testing. - Revised storage SOPs. | Warranty claims dropped 60%. |
4 | Hood warping post-oven | Method: Uneven heating in curing oven. | DMAIC (Six Sigma) | - Redesigned oven airflow (DOE optimized). - Added IR sensors for temp uniformity. | Warping eliminated (CpK >1.67). |
5 | Gap misalignment | Machine+Method: Fixture wear + loose SOPs. | Kaizen + FMEA | - Replaced worn fixtures. - Updated control plan with 3x/day checks. | Gap compliance reached 99.2%. |
4M Breakdown with Automotive Examples
Man (Operator)
Issue: Scratches from jewelry/tools.
Solution: Poka-yoke (tool-less gloves + magnetic wristbands).
Machine
Issue: Stamping press overloading.
Solution: Predictive maintenance (vibration sensors + IoT alerts).
Material
Issue: Thickness variation in aluminum sheets.
Solution: Supplier SPC + incoming inspection gates.
Method
Issue: Inconsistent torque sequence on hinges.
Solution: Digital torque wrenches with step-by-step guides.
Quality Tools Linked to 4M
Tool | Best for 4M Category | Example Application |
5 Whys | Man | Rapid RCA for human errors (e.g., misloading). |
FMEA | Machine + Method | Risk-ranking oven failures or stamping cracks. |
8D | Material | Contaminated paint from supplier resolution. |
SPC | Machine | Monitoring press tonnage stability. |
Kaizen | All 4Ms | Quick wins (e.g., ergonomic workstation redesign). |
Outcomes
Cost savings: $250K/year from reduced rework (Case 4).
IATF 16949 compliance: All cases closed with documented CAPAs.
Customer PPM: Improved from 1,200 to 150 PPM (Cases 1+3).
Visual Workflow for Defect Resolution
text
Defect → 4M Analysis → Tool Selection → Countermeasure → Standardize Example: Hood dents → Man (handling) → 5 Whys → Foam padding → Updated work instructions.
Need detailed templates (e.g., 4M checklist, FMEA worksheet) or DMAIC project reports for these cases